Nubaria Power Plant I & II 2×750 MW CCP.
Owner: | West Delta Electricity Production Company (WDEPC). |
Main Contractor: | ALSTOM - DSD. |
Quantity: | 4500 Ton |
Execution Period: | 14 Months 1/2005 - 3/2006 |
Description
ARCONS Scope of work Installation of Harps, Baffles, Inlet Duct, Oulet Duct, 4x HRSG, Casing and Steel Structure for 2x750 MW Combined Cycle Project.
ARCONS Scope of work Installation of Harps, Baffles, Inlet Duct, Oulet Duct, 4x HRSG, Casing and Steel Structure for 2x750 MW Combined Cycle Project.
Share
- Tags
- BafflesCasingHarpsInlet DuctOulet Duct
- Client
- ALSTOM - DSD.
- Release Date
- 2006